Chemical Energy

Final Acceptance Received from Nucor Kankakee

INTECO PTI was awarded the contract to install a chemical energy system into the EAF at Nucor Kankakee mid-2018.  The furnace at Nucor Kankakee has never used chemical energy in the EAF.  The new system is composed of a valve train for oxygen and gas flow control, PLC supervisory system and three Jet Boxes and burners installed on the EAF sidewall.  The equipment delivery date was August 2018 and the system start up started in September 2018.

After a ramp up period Nucor Kankakee awarded Inteco PTI the Final Acceptance Certificate. Inteco PTI will continuously provide process support as well as necessary spare parts and repairs. 